The name of works |
Terms of performance |
Filling the technical application on development of a lay-out of the exhibition |
8 weeks prior to the beginning of installation of an exposition |
The coordination of details on technical requirements |
7 weeks prior to the beginning of installation of an exposition |
The conclusion of the contract |
7 weeks prior to the beginning of installation of an exposition |
Delivery of lay-out of stands:
- Service blocks |
4 weeks prior to the beginning of installation of an exposition |
Accounting on building |
Within 1 week after delivery of lay-out by the customer |
The coordination and the statement of accounting |
Within 1 week after delivery of lay-out by the customer |
Preparation of assembly plans |
Within 1 week after delivery of lay-out by the customer |
Verification and updating of assembly plans |
3 weeks prior to the beginning of installation of an exposition |
Delivery of materials for manufacture |
2 weeks prior to the beginning of installation of an exposition |
A complete set of an exhibition |
1 week prior to the beginning of installation of an exhibition |
Installation / dismantle of an exhibition |
In terms established by the organizer of the exhibition |
![]() |
![]() |